Insights Reporting - Data Warehouse

95%

Status

In Process [In Process]

95% complete, updated on Thu 8/20/26 10:34 PM by Jeannette Jasmin Ramos

Research and Planning provided feedback on updates needed to the enrollment reports. The consultant is working on implementing changes and will inform the team when they are ready to test. 

Validation of these reports is the remaining workstream activity. 

Details

Dates
Tue 7/22/25 - Wed 4/1/26
Acct/Dept
Technology Services & Support
Type
Information Technology Projects / Information Technology Projects
Health
Green - On track
Program(s)
Classification
Medium Project (81–150 hours)
Requirements
Key stakeholders—all functional areas—formally sign off on the integration, confirming that all success criteria have been met.
Created
Tue 7/22/25 3:47 PM
Modified
Thu 8/20/26 10:34 PM
Benefit/Purpose
Briefly describe what you hope to achieve by executing the project, including anticipated benefits.
The purpose of this project is to implement Ellucian's reporting tool to ensure Solano's reporting needs are met and future-proof (SaaS compliant). Existing Argos reports will be converted to point to SaaS/Insights data, preserving current reporting needs.
Deliverables Requested
List or summarize all specific deliverables resulting from this project. What will the project produce or deliver? These should include items that are specific, measurable, achievable, realistic, and time bound.
(1) Configuration and deployment of Insights environment including
(a.) Access to insights extensibility tools
(b.) Access to Experience cards
(2) Configuration of display rules, parameters, custom datasets and point in time data captures
(3) Complete security setup
(4) Report development of all necessary Solano reports
(5) Ellucian Report development: 4 Small, 4 Medium, and 2 Large reports
(6) Report development training focused on the Insights Report Builder/Guided User Interface

Program Review & Participatory Governance

Budget Health
Green
Resource Health
Green
Schedule Health
Green

Goals

  1. Project improves overall data quality for institutional reporting needs.

Alternate Manager(s)

Sponsor